Project progress Světlá nad Sázavou
Published by: 06.02.2021 12:06:11Dear friends,
hereby we would like to inform you about the progress of our development project in Světlá nad Sázavou, where our fund is preparing a modern residential unit on a plot of 4000m2.
The current timeline is planned as follows:
- Q3/2021 - design development for study
- Q2/2022 - processing of planning permission and building permits
- Q2/2022 - start of construction and start of sales of residential units
- Q3/2023 - complete completion of construction
- Q3/2023 - approval and handover of the units to the owners
For further information, please contact us.